Purpetruboprovodstroi To Construct Gathering Pipelines for Sibneft-Noyabrskneftegaz

NGSK Purpetruboprovodstroi concluded the second contract with JSC Sibneft-Noyabrskneftegaz for the construction of 70.6 km of 110 mm to 530 mm diameter gathering pipelines. The contract value amounted 166.41 million Rubles.

PTPS commenced construction and installation works at the Sibneft-NNG fields in the beginning of February under a preliminary arrangement with the customer. The facilities are scheduled for commissioning in September 2006. The works are underway at six fields of Sibneft-NNG, i.e. Muravlenkovskoye, Usmeiskoye, Kraineye, Sutorminskoye and Vostocho-Pyakutinskoye.